Survey and removal before a bathroom remodel goes out to bid
Example project
- Home
- 1950s single-story house in Kirkland
- Original request
- A new hall bathroom, with bids from three remodelers
- Testing
- Floor tile, its glue, wall texture and tub-wall compound sampled before any remodeler visits
- Found
- Two positives: the black glue under the small floor tile and the seams of the tub wall
- Work
- About 45 sq ft of floor and 70 sq ft of tub wall removed inside plastic
- Timeline
- Survey a week ahead of the bids; removal in two days
- Cost
- $4,200
In this example, the owners of a 1950s house want three remodelers to bid on a new hall bathroom. They have the survey done first, so every bid starts from the same facts: asbestos in the glue under the small floor tile and in the joint compound around the tub, none in the wall texture.